Concrete repair work scheduled for Harmony Road (Timberline Road to I-25) beginning Monday, March 25, 2024

Released on Tuesday, March 19, 2024

Contact Information

  • Darren Moritz, Street Maintenance Program Manager, 970-556-1495, DMoritz@fcgov.com

Images

  • Media image thumbnail

FORT COLLINS – The City of Fort Collins Streets Department will begin concrete repair work on Harmony Road beginning Monday, March 25, 2024, weather permitting.

The work will move along Harmony Road from the Timberline Road intersection east toward the area of Strauss Cabin Road, approaching I-25.

Concrete repairs will be followed by asphalt milling and paving starting tentatively in late April 2024.

Lane closures will be in effect during this work and drivers should be aware of changing traffic patterns. Access to residences and businesses will be maintained.

The initial concrete repair work is expected to last 2-3 weeks. In late April, crews will mill and overlay Harmony Road with a new surface. Officials anticipate this phase of the work taking about six weeks to complete. Construction timelines are weather dependent.

Work Zone Information

Typical working hours are Monday through Friday from 8:30 a.m. to 3:30 p.m., however work may occur outside these times or on the weekends to expedite the project. Alternate routes are suggested to avoid the construction zones.

For more information about the Street Maintenance Program, please visit fcgov.com/smp or call the Streets Department at 970-221-6615.