Skip to main content

Halligan Water Supply Project

 Contact Information

 Halligan and NISP

 Receive Periodic Email Updates

Updates

Draft Environmental Impact Statement Released

Draft Environmental Impact Statement Released
 

The draft EIS for the Halligan Water Supply Project was released Friday, Nov. 22 This is a critical milestone in the federal permitting process. The EIS describes the project, other water supply alternatives considered and the potential impacts of each. 

The draft EIS is available online and physical copies are available at the following locations:

  • CSU Morgan Library, 1201 Center Ave., Fort Collins, CO 80523
  • Poudre River Public Library District-Old Town Library, 201 Peterson St., Fort Collins, CO 80524
  • Poudre River Public Library-Harmony Library, 4616 S. Shields St., Fort Collins, CO 80526
  • UNC, James A. Michener Library, 14th Ave. and 20th St., Greeley, CO 80639
  • U.S. Army Corps of Engineers, Denver Regulatory Office, 9307 S. Wadsworth Blvd., Littleton, CO 80128

A public hearing was held Jan. 13. All written comments on the draft EIS must be submitted to Mr. Cody Wheeler, U.S. Army Corps of Engineers, Denver Regulatory Office, 9307 S. Wadsworth Blvd., Littleton, CO 80128 or to TldPLkhhbGxpZ2FuRUlTQHVzYWNlLmFybXk= by Feb. 26, 2020. (Note: this date reflects a 30-day extension from the Corps.)

Details

Conceptual Mitigation Plan Available for Feedback

Conceptual Mitigation Plan Available for Feedback
 

The Conceptual Mitigation Plan for the Halligan Water Supply Project was released Nov. 22, 2019 with the draft EIS. A public hearing was held Jan. 13. All written comments to be considered for the official record on the draft EIS must be submitted to Mr. Cody Wheeler, U.S. Army Corps of Engineers, Denver Regulatory Office, 9307 S. Wadsworth Blvd., Littleton, CO 80128 or to TldPLkhhbGxpZ2FuRUlTQHVzYWNlLmFybXk=.mil by Feb. 26, 2020. (Note: this date reflects a 30-day extension from the Corps.)

View Mitigation Plan

Cost Update

Fort Collins Utilities has updated the cost estimate for the Halligan Water Supply Project. Based on information known at this time, current estimates indicate a probable cost of $120 million. However, costs could vary between $100 million to $150 million as the project scope and schedule are more clearly defined. 

Learn More

Events

There are no events scheduled at this time. Sign up for email updates to be notified of any up upcoming open houses, information sessions or public hearings.