Skip to main content

OpenBook

Departments Ut Distribution System Div Construction Services
Vendor/Payee Comments Date Amount
CONNELL RESOURCES INC
[P.O. # 1509641]
CONSTRUCTION SERVICES Nov-02-2015 $3,447.86
CONNELL RESOURCES INC
[P.O. # 9146985]
Change Order1 Dec-10-2015 $17,636.79
LOBOS STRUCTURES
[P.O. # 9156487]
W. Mulberry @ New Mercer Ditch Feb-09-2016 $74,947.20
CONNELL RESOURCES INC
[P.O. # 9160515]
City Bridge Olive/Loomis Imprv Feb-18-2016 $1,920.00
CONNELL RESOURCES INC
[P.O. # 9160515]
City Bridge Olive/Loomis Imprv Mar-08-2016 $25,168.00
CONNELL RESOURCES INC
[P.O. # 9161608]
CONSTRUCTION SERVICES Mar-10-2016 $8,780.00
CONNELL RESOURCES INC
[P.O. # 9160794]
CONSTRUCTION SERVICES Mar-21-2016 $119,286.36
MORTENSON CONSTRUCTION
[P.O. # 9151772]
Adding retainage to be paid by Apr-19-2016 $2,185.45
CONNELL RESOURCES INC
[P.O. # 9160794]
CONSTRUCTION SERVICES Apr-28-2016 $45,021.01
CONNELL RESOURCES INC
[P.O. # 9160794]
CONSTRUCTION SERVICES Apr-28-2016 $-45,021.01
CONNELL RESOURCES INC
[P.O. # 9160794]
CONSTRUCTION SERVICES May-05-2016 $42,769.96
CONNELL RESOURCES INC
[P.O. # 9160794]
CONSTRUCTION SERVICES May-26-2016 $25,100.28
CONNELL RESOURCES INC
[P.O. # 9160794]
CONSTRUCTION SERVICES May-26-2016 $-68,943.68
CONNELL RESOURCES INC
[P.O. # 9160794]
CONSTRUCTION SERVICES May-26-2016 $68,943.68
CONNELL RESOURCES INC
[P.O. # 9171348]
ALTA VISTA Apr-03-2017 $14,199.32
CONNELL RESOURCES INC
[P.O. # 9171348]
ALTA VISTA Apr-25-2017 $19,695.24
CONNELL RESOURCES INC
[P.O. # 9166717]
NECCO Phase 1b construction May-25-2017 $26,067.46
CONNELL RESOURCES INC
[P.O. # 9172445]
WO #201706 PINE STREET WATER Jun-26-2017 $900.36
CONNELL RESOURCES INC
[P.O. # 9166717]
NECCO Phase 1b construction Jul-03-2017 $17,932.73
CONNELL RESOURCES INC
[P.O. # 9166717]
NECCO Phase 1b construction Jul-21-2017 $11,770.36
CONNELL RESOURCES INC
[P.O. # 9172445]
WO #201706 PINE STREET WATER Aug-07-2017 $9,396.09
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9174995]
WO #201708 AZALEA DRIVE Aug-11-2017 $25,931.36
CONNELL RESOURCES INC
[P.O. # 9166717]
NECCO Phase 1b construction Aug-18-2017 $200,000.00
CONNELL RESOURCES INC
[P.O. # 9166717]
NECCO Phase 1b construction Aug-18-2017 $2,858.45
CONNELL RESOURCES INC
[P.O. # 9172445]
WO #201706 PINE STREET WATER Aug-31-2017 $859.53
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9174995]
WO #201708 AZALEA DRIVE Sep-11-2017 $58,934.41
Total (of all records): $ 709,787.21