Note: denotes a purchasing card expense.
Vendor/Payee Comments Date Amount
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9155458]
CONSTRUCTION CONTRACTS Oct-12-2015 $53,445.56
CH2M HILL INC
[P.O. # 9135679]
CONSTRUCTION CONTRACTS Oct-15-2015 $586.99
MSI TEC INC MSI TEC TAX REFUND INV#10 Oct-30-2015 $-31.75
MSI TEC INC MSI TEC TAX REFUND INV#10 Oct-30-2015 $-5.95
MSI TEC INC 4 POE SWITCH/WTF CONSTRUC Oct-30-2015 $1,196.75
MSI TEC INC 100-240VAC/WTF CONSTRUCTI Oct-30-2015 $273.78
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9150551]
CONSTRUCTION CONTRACTS Nov-17-2015 $33,809.43
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9152300]
CONSTRUCTION CONTRACTS Nov-17-2015 $9,775.22
CH2M HILL INC
[P.O. # 9135679]
CONSTRUCTION CONTRACTS Nov-17-2015 $904.59
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9155458]
CONSTRUCTION CONTRACTS Nov-17-2015 $34,252.17
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9152300]
CONSTRUCTION CONTRACTS Nov-18-2015 $18,663.35
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9155458]
CONSTRUCTION CONTRACTS Dec-07-2015 $5,792.00
GAN*1021COLORADOANADV Coloradoan Advertisement Dec-29-2015 $29.26
GAN*1021COLORADOANADV GAN*1021COLORADOANADV PO9 Jan-28-2016 $23.56
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9150551]
CONSTRUCTION CONTRACTS Feb-17-2016 $7,010.37
CAROLLO ENGINEERING
[P.O. # 9152223]
CONSTRUCTION CONTRACTS Feb-29-2016 $140.20
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9150551]
CONSTRUCTION CONTRACTS Mar-21-2016 $5,000.00
CAROLLO ENGINEERING
[P.O. # 9152223]
CONSTRUCTION CONTRACTS Mar-22-2016 $4,745.00
GAN*1021COLORADOANADV COLORADOAN ADV PO9150551 Apr-29-2016 $24.37
CAROLLO ENGINEERING
[P.O. # 9152223]
CONSTRUCTION CONTRACTS May-05-2016 $4,106.20
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9162138]
CONSTRUCTION CONTRACTS May-13-2016 $136,751.00
CAROLLO ENGINEERING
[P.O. # 9152223]
CONSTRUCTION CONTRACTS May-20-2016 $782.30
CITY OF FORT COLLINS MISCELLAN
[P.O. # 9163614]
CONSTRUCTION CONSTRACTS Jun-13-2016 $36,162.96
KORBY LANDSCAPING LLC
[P.O. # 9157414]
LANDSCAPE-EXTRA AREAS Jul-05-2016 $2,772.00
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9168197]
CARBON DIOXIDE TANK RELOCATION Feb-13-2017 $6,128.90
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9168197]
CARBON DIOXIDE TANK RELOCATION Mar-21-2017 $89,219.90
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171148]
Carbon Dioxide Tank Relocation Mar-21-2017 $46,850.71
CTL/THOMPSON INC
[P.O. # 1703972]
FCWTP Carbon Dioxide Tank May-01-2017 $680.00
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171148]
Carbon Dioxide Tank Relocation May-01-2017 $55,599.44
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171148]
Carbon Dioxide Tank Relocation May-01-2017 $45,710.77
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9168197]
CARBON DIOXIDE TANK RELOCATION May-01-2017 $52,970.91
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171885]
Contractor Construction May-24-2017 $15,980.00
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9168197]
CARBON DIOXIDE TANK RELOCATION May-25-2017 $7,806.29
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171885]
Contractor Construction Jun-29-2017 $2,299.00
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171148]
Carbon Dioxide Tank Relocation Jul-19-2017 $24,023.85
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171148]
Carbon Dioxide Tank Relocation Jul-19-2017 $14,623.23
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171148]
Carbon Dioxide Tank Relocation Aug-23-2017 $9,832.00
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171281]
Contractor Construction Sep-05-2017 $10,536.04
HYDRO CONSTRUCTION CO INC (WIR
[P.O. # 9171281]
Contractor Construction Sep-21-2017 $8,062.37
GAN*1021COLORADOANADV PO9171148 AD Sep-29-2017 $25.96
Total (of all records): $ 746,558.73