Vendor/Payee Comments Date Amount
E-Z POUR READY MIX
[P.O. # 9124322]
CEMENT & ASPHALT Aug-06-2012 $450.50
MARTIN MARIETTA MATERIALS
[P.O. # 9124352]
CONCRETE & ASPHALT Aug-08-2012 $886.19
MARTIN MARIETTA MATERIALS
[P.O. # 9125569]
CEMENT & ASPHALT Oct-22-2012 $372.75
MARTIN MARIETTA MATERIALS
[P.O. # 9125569]
CEMENT & ASPHALT Oct-22-2012 $1,359.42
MARTIN MARIETTA MATERIALS
[P.O. # 9125569]
CEMENT & ASPHALT Oct-22-2012 $-1,359.42
MARTIN MARIETTA MATERIALS
[P.O. # 9125569]
CEMENT & ASPHALT Oct-22-2012 $1,359.42
AGGREGATE INDUSTRIES INC
[P.O. # 9125961]
CEMENT & ASPHALT Nov-19-2012 $1,529.20
E-Z POUR READY MIX
[P.O. # 9126198]
CONCRETE & ASPHALT Dec-03-2012 $162.00
E-Z POUR READY MIX
[P.O. # 9126198]
CONCRETE & ASPHALT Dec-03-2012 $196.00
BESTWAY CONCRETE CO
[P.O. # 9126230]
CONCRETE & ASPHALT Dec-04-2012 $320.00
E-Z POUR READY MIX
[P.O. # 9126382]
CONCRETE & ASPHALT Dec-13-2012 $459.00
MARTIN MARIETTA MATERIALS
[P.O. # 9126450]
CEMENT & ASPHALT Dec-18-2012 $532.50
E-Z POUR READY MIX
[P.O. # 9130573]
CONCRETE & ASPHALT Jan-25-2013 $238.50
Total (of all records): $ 6,506.06