Expense Type Department Date Amount
Concrete & Asphalt Streets Aug-15-2013 $-158,350.16
Sand & Gravel Supplies Parks Aug-13-2013 $23.98
Sand & Gravel Supplies Utilities Water Production Div Aug-12-2013 $83.95
Sand & Gravel Supplies Parks Aug-13-2013 $85.60
Sand & Gravel Supplies Utilities Distribution System Div Aug-26-2013 $99.33
Concrete & Asphalt Streets Aug-05-2013 $112.22
Sand & Gravel Supplies Utilities Distribution System Div Aug-26-2013 $112.26
Concrete & Asphalt Streets Aug-20-2013 $146.48
Sand & Gravel Supplies Utilities Drainage System Div Aug-26-2013 $158.27
Concrete & Asphalt Streets Aug-20-2013 $159.13
Sand & Gravel Supplies Utilities Distribution System Div Aug-26-2013 $175.95
Sand & Gravel Supplies Utilities Distribution System Div Aug-26-2013 $345.36
Concrete & Asphalt Streets Aug-05-2013 $349.19
Sand & Gravel Supplies Utilities Distribution System Div Aug-26-2013 $353.44
Concrete & Asphalt Streets Aug-05-2013 $382.92
Sand & Gravel Supplies Utilities Collection System Div Aug-26-2013 $393.50
Concrete & Asphalt Streets Aug-12-2013 $434.48
Concrete & Asphalt Traffic Aug-27-2013 $616.00
Concrete & Asphalt Streets Aug-28-2013 $623.32
Concrete & Asphalt Streets Aug-28-2013 $832.67
Sand & Gravel Supplies Utilities Distribution System Div Aug-26-2013 $865.31
Sand & Gravel Supplies Utilities Collection System Div Aug-26-2013 $1,069.46
Concrete & Asphalt Streets Aug-28-2013 $1,285.71
Concrete & Asphalt Streets Aug-20-2013 $1,336.77
Concrete & Asphalt Streets Aug-12-2013 $1,442.85
Concrete & Asphalt Streets Aug-05-2013 $1,614.30
Sand & Gravel Supplies Utilities Distribution System Div Aug-05-2013 $1,924.62
Concrete & Asphalt Streets Aug-12-2013 $2,153.44
Concrete & Asphalt Streets Aug-05-2013 $2,209.78
Concrete & Asphalt Streets Aug-05-2013 $3,846.76
Concrete & Asphalt Streets Aug-05-2013 $3,992.74
Concrete & Asphalt Streets Aug-22-2013 $5,110.56
Concrete & Asphalt Streets Aug-05-2013 $5,967.27
Concrete & Asphalt Streets Aug-20-2013 $6,449.97
Concrete & Asphalt Streets Aug-12-2013 $7,792.97
Concrete & Asphalt Streets Aug-13-2013 $12,182.95
Concrete & Asphalt Streets Aug-12-2013 $20,971.37
Street & Bridge Maint Serv Streets Aug-22-2013 $24,646.02
Concrete & Asphalt Streets Aug-22-2013 $29,764.74
Concrete & Asphalt Streets Aug-22-2013 $33,366.09
Concrete & Asphalt Streets Aug-20-2013 $43,393.39
Concrete & Asphalt Streets Aug-20-2013 $46,116.07
Concrete & Asphalt Streets Aug-20-2013 $80,725.80
Concrete & Asphalt Streets Aug-28-2013 $96,283.06
Concrete & Asphalt Streets Aug-13-2013 $141,649.84
Concrete & Asphalt Streets Aug-06-2013 $158,350.16
Concrete & Asphalt Streets Aug-28-2013 $184,746.17
Street & Bridge Maint Serv Streets Aug-22-2013 $468,426.33
Total: $ 1,234,822.39